Big Digital Energy reports 17 MW energized at Hood County with pathway to 111 MW grid capacity
The site is about 50 acres with a 138 kV interconnection and 3 natural gas pipelines that can support behind-the-meter generation toward ~300 MW total campus capacity. Pathway to 111 MW is subject to ERCOT validation.
- Size
- 111 MW
- Place
- Hood County, TX
- Companies
- 10NetZero, Big Digital Energy
- Source
- Big Digital Energy, Inc. 8-K, filed Nov 6, 2026