Grid-connected capacity rose from 129 to 169 MW in 2026. The pipeline includes 148 MW of BGDE pipeline and 399 MW of SixThirtyAI power assets in development. BGDE targets $1B in project-level and platform financing.
BGDEBig Digital EnergySixThirtyAI
Source: Big Digital Energy, Inc. 8-K, filed Nov 6, 2026
The ~50-acre site, less than 40 miles from DFW, has a 138 kV interconnection and 3 natural gas pipelines on site. The 111 MW pathway is subject to ERCOT validation; it is a 50/50 JV with 10NetZero.
10NetZeroBGDEBig Digital EnergyERCOT
Source: Big Digital Energy, Inc. 8-K, filed Nov 6, 2026
The LOI covers initial deployment of 7,748 Nvidia B300 GPUs for training and inference, with $546M potential power-lease revenue to Texas Load House over 15 years. Capacity is expected available Q2 2027; BGDE owns 50% of Texas Load House and completion depends on definitive agreements, financing and approvals.
10NetZeroBGDEBig Digital EnergyNvidiaTensor IQTexas Load House
Source: Big Digital Energy, Inc. 8-K, filed Nov 6, 2026