The former industrial site has more than 250 buildable acres, an on-site energized substation, multiple high-voltage transmission lines and a direct regional transmission connection. The seller was granted a 6.8 % minority equity interest in the Justified Data Campus.
TeraWulf
Source: Terawulf Inc. 10-Q, filed Nov 6, 2026
Two miner buildings were repurposed or placed out of service during the nine months ended September 30, 2026 to support HPC development at the site. The company also has energized 145 MW of capacity across three buildings for bitcoin mining.
TeraWulf
Source: Terawulf Inc. 10-Q, filed Nov 6, 2026
The expansion is in PJM and subject to regulatory approval, which would supersede the firm 500 MW already approved. The initial 500 MW phase is targeted to ramp in Q4 2028, with a further 500 MW in 2029.
TeraWulf
Source: Terawulf Inc. 8-K, filed Nov 6, 2026
The 20-year lease has two 5-year extension options, with about $19B contracted revenue. Fluor is EPC contractor, Google provides credit support, the Kentucky PSC approved 482 MW of electric service, and phased delivery runs late 2027 through Q2 2028.
AnthropicFluorGoogleTeraWulf
Source: Terawulf Inc. 8-K, filed Nov 6, 2026
Of the 839 MW, 102 MW is operating and 737 MW is under construction. Tenants include Core42 and Fluidstack at Lake Mariner and Anthropic at Justified, with Google credit support.
AnthropicCore42FluidstackGoogleTeraWulf
Source: Terawulf Inc. 8-K, filed Nov 6, 2026