TeraWulf's Justified campus in Hawesville, Kentucky has 401 MW contracted critical IT leased to Anthropic
The 20-year lease has two 5-year extension options, with about $19B contracted revenue. Fluor is EPC contractor, Google provides credit support, the Kentucky PSC approved 482 MW of electric service, and phased delivery runs late 2027 through Q2 2028.
- Size
- 401 MW
- Place
- Hawesville, Kentucky
- Source
- Terawulf Inc. 8-K, filed Nov 6, 2026