Interconnecting Intelligence The facts on AI, from demand to buildout.

ComputeFiling

TeraWulf has energized 102 critical IT MW of HPC leasing capacity at Lake Mariner Data Campus as of September 30, 2026

Two miner buildings were repurposed or placed out of service during the nine months ended September 30, 2026 to support HPC development at the site. The company also has energized 145 MW of capacity across three buildings for bitcoin mining.

Size
102 MW
Place
Lake Mariner Data Campus, upstate New York
Companies
TeraWulf
Source
Terawulf Inc. 10-Q, filed Nov 6, 2026
Published here

Download share image

This fact was extracted from the source above and checked automatically: every number and company named here appears in it. Read the original before relying on it.