The South accounted for 55% of US data center construction in 2025.
Updates: yearly · Last checked Nov 21, 2026
Download imagePoint at the chart, or tap it, to see the values. The image is sized for X and LinkedIn, with source and address.Source: [9]Show the data
Year
South
Midwest
West
Northeast
US total
2025
$27.2 bn
$13.1 bn
$8.9 bn
$0.5 bn
$49.7 bn
2024
$17.2 bn
$9.5 bn
$7.6 bn
$0.5 bn
$34.8 bn
2023
$8.5 bn
$5.0 bn
$6.1 bn
$0.4 bn
$20.0 bn
2022
$4.7 bn
$3.5 bn
$4.3 bn
$0.1 bn
$12.6 bn
2021
$4.1 bn
$2.5 bn
$3.3 bn
$0.1 bn
$9.9 bn
2020
$4.5 bn
$2.6 bn
$1.9 bn
$0.3 bn
$9.2 bn
2019
$4.6 bn
$1.7 bn
$1.9 bn
$0.3 bn
$8.5 bn
Key figures
Total, latest (2025)
$49.7 bn
South, latest
$27.2 bn
Midwest, latest
$13.1 bn
West, latest
$8.9 bn
Total, first (2019)
$8.5 bn
Worked out from the chart's data, as of Nov 21, 2026.
How it's measured
The Census Bureau publishes the yearly value of private data center construction put in place in each of its four regions, starting with 2019.
Regions may not add to the national total because of rounding. The data refreshes when Census publishes each year's figures.
On the chart: Census first published data centers by region for 2019. Regions may not add to the US total because of rounding.
A third-party compute partner would own and operate the appliances, with capacity sold through third-party GPU marketplaces. The Company has no distributed compute revenue and no definitive agreements, and may determine not to proceed.
AMD's MI350P accelerator will be available in preview in the first half of 2027 for Windows Server 2025 and later. NVIDIA DGX Station for Windows, with the GB300 Grace Blackwell Ultra Desktop Superchip and up to 748 GB of coherent memory, will support Windows Server 2028 at general availability.
The campuses would be of approximately 1 GW each on 49 parcels of approximately 13,547 acres. Campuses after the first are conceptual, with no site control, permits, power, tenants or financing.
Feliz Realty and Altalab LLC (Mass) each hold 10%. Alpha Digital Voltz is contractual managing member and exclusive development and operations manager, subject to local approvals and delivery of usufruct land rights.
The estimate is preliminary, has not been validated by engineering, and may increase materially. Construction financing is not committed and the offering funds only pre-development.