How many data centers are being permitted in Loudoun County, Virginia?
Data center buildings permitted in Loudoun County, Virginia, in 2025 total 9.8 million sq ft, the most of any year.
Updates: about twice a year · Last checked Nov 21, 2026
Download imagePoint at the chart, or tap it, to see the values. The image is sized for X and LinkedIn, with source and address.Source: [11]Show the data
Permit year
Built
Under construction
Buildings
2026
0 sq ft
2,600,676 sq ft
9
2025
0 sq ft
9,772,654 sq ft
29
2024
2,790,188 sq ft
2,262,868 sq ft
17
2023
3,058,471 sq ft
1,244,161 sq ft
15
2022
5,575,806 sq ft
0 sq ft
21
2021
2,588,019 sq ft
0 sq ft
13
2020
4,314,366 sq ft
0 sq ft
23
2019
2,849,748 sq ft
0 sq ft
17
2018
4,146,335 sq ft
0 sq ft
21
2017
2,201,249 sq ft
0 sq ft
12
2016
1,620,483 sq ft
0 sq ft
7
2015
1,107,791 sq ft
0 sq ft
7
2014
910,199 sq ft
0 sq ft
7
2013
1,125,581 sq ft
0 sq ft
4
2012
788,900 sq ft
0 sq ft
2
2011
331,351 sq ft
0 sq ft
3
2010
618,720 sq ft
0 sq ft
4
2009
282,499 sq ft
0 sq ft
2
2008
503,303 sq ft
0 sq ft
3
2007
531,456 sq ft
0 sq ft
3
2006
286,865 sq ft
0 sq ft
1
2003
69,800 sq ft
0 sq ft
1
2001
228,747 sq ft
0 sq ft
2
2000
866,426 sq ft
0 sq ft
9
1999
563,445 sq ft
0 sq ft
6
1997
423,612 sq ft
0 sq ft
4
Key figures
Total, latest (2026)
2.6 mn sq ft
Under construction, latest
2.6 mn sq ft
Total, first (1997)
0.4 mn sq ft
Worked out from the chart's data, as of Nov 21, 2026.
How it's measured
Loudoun County publishes a map layer of existing and permitted data center buildings, with each building's size and the date its permit was issued. The chart adds up square feet by permit year and status, from the county's latest snapshot.
The county updates the snapshot a few times a year; the status shown is as of the snapshot date. Buildings with no permit date are left out of the chart and counted in the note.
On the chart: 2026 covers permits through Sep 1, 2026. 0.5 million sq ft of buildings with no permit date are left out. Total: 54.2 million sq ft in 245 buildings.
A third-party compute partner would own and operate the appliances, with capacity sold through third-party GPU marketplaces. The Company has no distributed compute revenue and no definitive agreements, and may determine not to proceed.
AMD's MI350P accelerator will be available in preview in the first half of 2027 for Windows Server 2025 and later. NVIDIA DGX Station for Windows, with the GB300 Grace Blackwell Ultra Desktop Superchip and up to 748 GB of coherent memory, will support Windows Server 2028 at general availability.
The campuses would be of approximately 1 GW each on 49 parcels of approximately 13,547 acres. Campuses after the first are conceptual, with no site control, permits, power, tenants or financing.
Feliz Realty and Altalab LLC (Mass) each hold 10%. Alpha Digital Voltz is contractual managing member and exclusive development and operations manager, subject to local approvals and delivery of usufruct land rights.
The estimate is preliminary, has not been validated by engineering, and may increase materially. Construction financing is not committed and the offering funds only pre-development.