Anthropic-Amazon New Carlisle is the largest AI data center Epoch AI tracks, at 1,037 MW.
Updates: when the source publishes · Last checked Nov 21, 2026
Download imagePoint at the chart, or tap it, to see the values. The image is sized for X and LinkedIn, with source and address.Source: [10]Show the data
Site
Owner
Used by
Place
Power
H100 equivalents
Capital cost
Anthropic-Amazon New Carlisle
Amazon
Anthropic
New Carlisle, IN
1,037 MW
818,428
$39.3 bn
Colossus 2
SpaceXAI
Anthropic, Cursor, SpaceXAI
Memphis, TN
946 MW
1,111,673
$35.8 bn
OpenAI Stargate Abilene
Oracle
OpenAI
Abilene, TX
824 MW
1,018,696
$31.2 bn
Microsoft Fairwater Atlanta
Microsoft
OpenAI, Microsoft
Fayetteville, GA
636 MW
768,769
$24.1 bn
DayOne Nusajaya
DayOne
Malaysia
473 MW
583,837
$17.9 bn
Meta Prometheus
Meta
Meta
New Albany, OH
471 MW
536,343
$17.8 bn
DayOne Kempas
DayOne
Johor, Malaysia
422 MW
480,639
$16.0 bn
Microsoft Fairwater Wisconsin
Microsoft
OpenAI, Microsoft
Mount Pleasant, WI
369 MW
445,680
$14.0 bn
Google Pryor (North)
Google
Google DeepMind
Pryor, OK
368 MW
636,685
$13.9 bn
Colossus 1
SpaceXAI
Anthropic
Memphis, TN
340 MW
275,796
$12.9 bn
Google New Albany
Google
Google DeepMind
New Albany, OH
333 MW
323,901
$12.6 bn
Google Columbus
Google
Google DeepMind
Columbus, OH
303 MW
331,986
$11.5 bn
Amazon Madison Mega Site
Amazon
Anthropic
Canton, MS
284 MW
214,348
$10.8 bn
CoreWeave Denton TX
CoreWeave
OpenAI
Denton, TX
262 MW
252,653
$9.9 bn
Bridge Data Centres MY06
ByteDance
ByteDance
Johor, Malaysia
243 MW
221,052
$9.2 bn
Key figures
Anthropic-Amazon New Carlisle · Amazon · New Carlisle, IN
1,037 MW
Colossus 2 · SpaceXAI · Memphis, TN
946 MW
OpenAI Stargate Abilene · Oracle · Abilene, TX
824 MW
Microsoft Fairwater Atlanta · Microsoft · Fayetteville, GA
636 MW
DayOne Nusajaya · DayOne · Malaysia
473 MW
Worked out from the chart's data, as of Nov 21, 2026.
How it's measured
Epoch AI's Frontier Data Centers database tracks large AI data centers using satellite imagery, permits, company statements and other public records, and estimates each site's current power.
Power, compute and cost are Epoch AI's estimates, not figures the companies report. The database is licensed under CC BY 4.0 and the data refreshes daily.
On the chart: Power, compute and cost are Epoch AI's estimates, not figures reported by the companies.
A third-party compute partner would own and operate the appliances, with capacity sold through third-party GPU marketplaces. The Company has no distributed compute revenue and no definitive agreements, and may determine not to proceed.
AMD's MI350P accelerator will be available in preview in the first half of 2027 for Windows Server 2025 and later. NVIDIA DGX Station for Windows, with the GB300 Grace Blackwell Ultra Desktop Superchip and up to 748 GB of coherent memory, will support Windows Server 2028 at general availability.
The campuses would be of approximately 1 GW each on 49 parcels of approximately 13,547 acres. Campuses after the first are conceptual, with no site control, permits, power, tenants or financing.
Feliz Realty and Altalab LLC (Mass) each hold 10%. Alpha Digital Voltz is contractual managing member and exclusive development and operations manager, subject to local approvals and delivery of usufruct land rights.
The estimate is preliminary, has not been validated by engineering, and may increase materially. Construction financing is not committed and the offering funds only pre-development.