The site moved to Columbus Light and Water's Large Data Service Rate (Schedule DCB) effective October 1, 2026, with contracted demand raised from 8.5 to 11 megawatts and no capital contribution to the utility. The avoided TVA charge of approximately $1.5 million per megawatt above the first five megawatts would total approximately $9 million for 11 megawatts.
Columbus Light and WaterPowerComputeTennessee Valley Authority Source: Powercompute, Inc. 8-K, filed Nov 13, 2026