The site moved to Columbus Light and Water's Large Data Service Rate (Schedule DCB) effective October 1, 2026, with contracted demand raised from 8.5 to 11 megawatts and no capital contribution to the utility. The avoided TVA charge of approximately $1.5 million per megawatt above the first five megawatts would total approximately $9 million for 11 megawatts.

Size
11 MW
Place
Columbus, Mississippi
Companies
Columbus Light and Water, PowerCompute, Tennessee Valley Authority
Source
Powercompute, Inc. 8-K, filed Nov 13, 2026
Published here

Download share image

This fact was extracted from the source above and checked automatically: every number and company named here appears in it. When the same fact turns up in another filing or post, that source is added here instead of a second copy. Read the original before relying on it.