Cerebras
Facts that name Cerebras, newest first.
Each block delivers 3.0 MW of total power and supports 2.5 MW of critical IT load for NVIDIA GB300 and Cerebras CS-3 systems. Blocks will be built in a new 65,000-square-foot Chesnee, South Carolina facility, with delivery over the next year.
BitSinkCerebrasNVIDIA
Source: AirJoule Technologies Corp. 8-K, filed Nov 16, 2026
The financing is contemplated to fund the Columbiana, Alabama project. The filing says Phase 1 and Phase 2 of the Columbiana campus are a Tier III data center development. It also references a commitment to purchase NVIDIA Vera Rubin systems and a Cerebras Agreement.
CerebrasDigi Power XNVIDIA
Source: Digi Power X Inc. 10-Q, filed Nov 13, 2026
Phase 1 fees average about $40 million per year, roughly $402 million over ten years. Phase 2 (25 MW) is conditional and would raise total contract value to approximately $1.07 billion. Tenant access to Phase 1 is expected December 15, 2026, with billing from January 2027.
CerebrasDigi Power X
Source: Digi Power X Inc. 8-K, filed Nov 13, 2026