TeraWulf signs definitive EPC agreement with Fluor for three data center buildings at Justified campus
The GMP-basis agreement covers engineering, procurement, construction, testing and commissioning, building on a limited notice to proceed announced in March 2026. Phased ready-for-service completions are expected from late 2027 through the second quarter of 2028.
- Place
- Hawesville, Kentucky
- Source
- Terawulf Inc. 8-K, filed Nov 4, 2026