TeraWulf executes Google credit support agreements for debt financing of approximately $19 billion Anthropic lease commitments in Kentucky
The three Credit Support Agreements for CB-1, CB-2 and CB-3 back project financing for the Justified Data Campus. The Anthropic lease is 20 years for approximately 401 MW of critical IT load, with delivery in phases from late 2027 through Q2 2028.
- Size
- $19 bn
- Place
- Hawesville, Kentucky
- Source
- Terawulf Inc. 8-K, filed Nov 4, 2026
- Published here
This fact was extracted from the source above and checked automatically: every number and company named here appears in it. When the same fact turns up in another filing or post, that source is added here instead of a second copy. Read the original before relying on it.