IREN's 2GW Sweetwater Hub gets conditional inclusion in ERCOT's Batch Zero process as base load

IREN reports more than 5GW of secured power and a >35GW development pipeline on more than 30,000 acres of land. Horizon 1 was delivered to Microsoft and Horizon 2-4 progressed to late-stage construction.

Size
2 GW
Place
Sweetwater, Texas
Companies
ERCOT, IREN, Microsoft
Source
IREN Ltd 8-K, filed Nov 5, 2026