Duos acquired the campus in July and installed more than 7 megawatts of new infrastructure in about 75 days. It targets total CapEx of approximately $6.5 million per megawatt for future sites.
Duos Technologies GroupNVIDIA
Source: Duos Technologies Group, Inc. 8-K, filed Nov 17, 2026
Axe will pay an additional $42.9 million in monthly installments of $715,000, with the balance due no later than September 30, 2027. Duos leases the GPUs back from Axe under an extended five-year agreement to serve the Columbus customer.
Axe ComputeDuos Technologies Group
Source: Duos Technologies Group, Inc. 8-K, filed Nov 17, 2026
The agreement is valued at more than $400 million in total contract value. Deployment is expected to begin in the second quarter of 2027, and Duos is developing the 20 megawatt site for the customer.
Duos Technologies Group
Source: Duos Technologies Group, Inc. 8-K, filed Nov 17, 2026
The cluster of 288 Supermicro NVIDIA B300 NVL8 servers sits in a Duos-operated data center with approximately 5 megawatts of committed power. The customer contract term was extended to five years, through 2031.
Axe ComputeDuos Technologies GroupNVIDIASupermicro