TerraVolt secures firm commitment for 55,000 MMBTU per day of natural gas for planned Southeast Idaho data center campus
In April 2026 the company signed a supply agreement with a natural gas marketing company for its planned behind-the-meter onsite power plant on the Northwest Natural Gas Pipeline. It paid a reservation fee of approximately $3,833,000 in May 2026 and delivered a $6,000,000 letter of credit in August 2026.