Black Hills signs long-term agreements with Google for Cheyenne, Wyoming data center served by 2.7 GW resource mix
In September 2026 the Company entered a LPCS agreement and a generation facilities agreement, both extending through December 2048. Energy service is expected to start in late 2027, with the data center's projected peak load reached by the end of 2030.
- Size
- 2.7 GW
- Place
- Cheyenne, Wyoming
- Companies
- Black Hills Corp, Google
- Source
- Black Hills Corp /Sd/ 10-Q, filed Nov 5, 2026
- Published here
This fact was extracted from the source above and checked automatically: every number and company named here appears in it. Read the original before relying on it.